Electrification of the Quarry in Govshut Village, Ahal Province, Turkmenistan
General Project Information:
The quarry in Govshut village is intended for the extraction and processing of stone raw materials used for the production of crushed stone and other construction materials.
The production facility includes crushing and screening equipment, conveyor systems, pumps and compressors, as well as auxiliary engineering systems requiring a stable and reliable power supply.
Location:
Ahal Province, Turkmenistan
Scope of Work:
The project included the development of the quarry’s power supply system based on a 110/35/10 kV, 10 MVA substation, providing connection to the high-voltage grid, voltage transformation, and distribution of electrical power.
Equipment Supply and Installation:
- Supply and installation of the 110/35/10 kV, 10 MVA power transformer;
- Supply and installation of substation equipment;
- Installation of electrical connections at 110, 35 and 10 kV voltage levels;
- Laying and connection of power and control cables;
- Grounding of electrical equipment.
Testing and Commissioning:
- Inspection and electrical testing of the power transformer and substation equipment;
- Inspection of electrical connections and the grounding system;
- Commissioning works;
- Comprehensive inspection and preparation of the substation for operation.